Drywall
Drywall is stocked in the home. Insulation, gas meters and permanent power connections are installed. It often takes two full days to hang interior drywall. Next, drywall taping and finishing are scheduled to take five days and blown insulation is installed. After the interior walls are touched up, the walls and ceiling are textured.
Quality Checkpoint:
Upon clean up of drywall debris, Construction Manager check all walls and ceilings for finish and consistency.